1,745 gigawatts are stuck waiting to plug into the US grid

America's interconnection queues hold 1.3× the capacity of every power plant in the country. Historically, only 21% of requests get built.

Outerview Research · 2026-10-31 · 6 min read
1,745 GWwaiting to connect to the US grid
1,745 GW
of power plants and batteries waiting in US interconnection queues
1.3×
the entire installed US fleet (1,377 GW)
21%
of projects that applied in 2005–2018 were ever built
4,396 GW
withdrawn since 1995, about 8× what has been built

Before a power plant can sell electricity it needs permission to connect to the grid. The waiting lists for that permission, called interconnection queues, have become the single biggest bottleneck in American energy. At the end of 2025, 1,745 GW of projects were actively waiting. That is 1.3 times the capacity of every power plant in the country combined.

What happens to a queue request

Share of requests by outcome, by the year they entered the queue

  • Built (operational)
  • Withdrawn
  • Still waiting

Source: Berkeley Lab “Queued Up” interconnection data (through 2025) via Outerview energy_interconnection_projects

Most requests never become power plants. Of projects that entered the queues between 2005 and 2018, which have had at least seven years to finish, only 21% were built. The rest were withdrawn, often after years of studies, when the upgrade bill for the grid came back too high. Developers respond by filing speculative requests in many places at once, which clogs the queue further.

Completion rate by technology

Share of 2005–2018 requests now operating

Nuclear58.0%
Other32.5%
Gas30.8%
Wind20.2%
Storage16.7%
Hybrid + storage15.7%
Solar15.6%
Offshore wind4.4%

Source: Berkeley Lab “Queued Up” interconnection data (through 2025) via Outerview energy_interconnection_projects

What's waiting, and where

The active queue by technology

GW actively waiting at the end of 2025

  • 25%Hybrid + storage
  • 23%Solar
  • 23%Storage
  • 14%Gas
  • 10%Wind
  • 3%Other
  • 1%Offshore wind
  • 1%Nuclear
  • Each square = 1% of active capacity

Source: Berkeley Lab “Queued Up” interconnection data (through 2025) via Outerview energy_interconnection_projects

Largest queues by grid operator

GW actively waiting, end of 2025

ERCOT408
MISO348
SPP151
PJM131
CAISO128
BPA89
PacifiCorp49
APS48
NVE35
SOCO31
Duke30
NYISO27

Source: Berkeley Lab “Queued Up” interconnection data (through 2025) via Outerview energy_interconnection_projects

Texas (ERCOT) has the largest active queue, 408 GW, and also the fastest one, because its "connect and manage" rules let projects plug in first and accept curtailment later. PJM, the grid serving 65 million people from Chicago to Washington, reformed its process in 2023–24 after its queue stalled for years. Our view: interconnection reform is the highest-leverage energy policy left in the US. It decides whether the demand surge is met by new solar and storage that's already waiting, or by whatever can jump the line.